Build a Gantt chart in Power BI with the new native visual
Power BI's October 2026 update finally ships a Gantt chart as a core visual, in preview. How to turn it on, feed it tasks, milestones and progress, group and colour it, and where its limits are.
Power BIFix a problem4 min read
Project timelines in Power BI have always meant installing a custom visual. The October 2026 update changes that: a Gantt chart is now a core visual, in preview, with duration bars, progress, milestones, grouping, extra task-list columns and a zoomable axis — built in, nothing to import.
Turn the preview on
- In Power BI Desktop, go to File > Options and settings > Options > Preview features and enable the Gantt visual.
- Restart Power BI Desktop — the option takes effect after the restart.
- The visual appears in the Visualizations pane, marked (Preview).
Note
Preview visuals can change before general availability — fine for internal reports, worth a second thought on anything contractual.
The fields that drive it
- Task label
- Start and End dates
- Progress measure
- Groups and columns
The only required field is the task label — one row per task. Everything else is additive:
- Start and End draw the duration bar. Both accept measures, which is how you control date aggregation at category levels.
- A milestone is a Start with a blank End. That rule is also the trick for milestone flags: write an End measure that returns blank when your data marks the row as a milestone, and the visual draws a diamond instead of a bar.
- Columns beside the task list show details like owner, status or duration. To show subtotals at category levels, a column needs to be a measure or an aggregation. Links can display as icons instead of text.
- Extra tooltip fields add context without adding visible columns.
Progress and grouping
Add a measure that returns each row's percentage complete and the bar shows it. Two styles are built in: a translucent white overlay on the bar, or a colour fill inside bordered bars — and the fill's share of the bar's height is configurable in the Format pane.
Group tasks with up to three category levels. Colouring then works top-down: set one colour under Rows > Color and the visual cascades it — solid task bars and milestones, and progressively lighter category row backgrounds (70%, 80%, 90% transparency by level). For per-category or per-task colours, switch the level to More granular; conditional formatting is available too, and every element can opt out of the cascade.
The axis, weekends and zoom
- Auto-scale picks years, months or days from the range, the visual's size and the zoom level — and never goes finer than days, though bars can show partial days when your dates carry times.
- Turning auto-scale off gives a fixed two-level axis — months over years, or even the same unit twice with different formats, such as weekday names over day numbers.
- Shade days marks chosen weekdays — weekends, typically — as shaded columns.
- The zoom slider lets readers focus on a window of the timeline and return to the full range without leaving the visual.
Limits to plan around
- 1,000 rows is the ceiling. A portfolio-scale schedule needs filtering or a different approach.
- No task dependencies, no connector lines between tasks, and no critical path.
- No baselines — plan-versus-actual comparisons aren't in the preview.
- Measure display formatting may not carry into tooltips and columns; set Data format on the Format pane's General tab as the workaround.
- With More granular colours, static colours can skip some category levels or tasks that appear in several categories — Microsoft points to conditional formatting instead.
If those gaps matter to your schedule — dependencies, critical path, baselines — a custom Gantt visual remains the route for now; the native visual covers the plain-timeline cases that used to require one.