Pulse Gantt demo

Try the Power BI visual with sample data. Put columns in the field wells, load an example or a common mistake, and change the format. The chart below is the visual's own code, running in a stand-in for Power BI.

Examples

Common mistakes

The visual

Hover for tooltips, select rows, right-click, collapse groups.

Visualizations

Data

Select a column, then a well. Or drag it into a well.

Pulse Gantt field guide

What to put in each field of Pulse Gantt by LowCodeStacks, what the visual does with it, and the mistakes that are easy to make. Every statement here was checked against the visual's code (src/model.ts, src/visual.ts, src/settings.ts and capabilities.json, version 1.0.0.0). To see any of it working, run the demo (npm run demo, then open demo/index.html).

The short version

You wantPut in these fields
A bar per taskTask, Start, End
Phases with progressadd Group by and Progress
Connector lines and the critical pathadd Task ID and Predecessors
What slipped against the planadd Baseline start and Baseline end
A milestonea Start with a blank End

How Power BI hands the data over

The fields

Task

Group by

Start

End

Progress

Task ID

Predecessors

Baseline start

Baseline end

Critical flag

Columns

Tooltips

The float engine and the critical path

With dependencies bound, the visual works out each task's float: the working days it can slip before it pushes a successor, chained through to the project end. For a task with successors, float is the smallest of (working days between its end and the successor's start, plus that successor's float). A task with no successors floats against the project end, which is the latest End (or a milestone's Start) in the data. Working days are Monday to Friday; there are no holidays, and the days counted are those strictly between the two dates.

The header reads the result: Finish (the project end), the slip against baseline (the worst slip on the critical path), and, when the project is late, the driver: the earliest-starting task that slipped at least as much. When no critical task has a baseline, the slip compares the project end with the latest baseline date in the data.

The format options

CardOptions (default)
Critical pathCritical within, working days of float (0, from 0 to 30); Dim non-critical tasks (off); Hatch critical bars (off; hatches the filled, progress part of a critical bar, so it needs Progress)
Status coloursCritical path, Done, In progress, Slip vs baseline. On a dark background the visual uses lighter versions of the defaults until you pick your own.
HeaderShow header (on; needs the visual at least 160 px tall); Schedule health chips (on); Verdict sentence (on)
Task listWidth (360, from 160 to 800; it never takes more than 55% of the visual's width, or less than 160 px); Start and end columns (off); Slip column (on); Progress column (on). Columns that don't fit beside the task names are left out.
DependenciesShow dependencies (on); Critical chain only (off)
BaselineShow baseline (on); Slip badges (on)
AxisToday line (on); Weekend shading (on; drawn when days are at least 4 px wide)
CanvasBackground (white; a dark colour switches the visual to its dark look); Row height (36, from 24 to 64); Animate on load (on)

In Windows high contrast, the visual uses only the two colours Power BI gives it, drops the weekend shading and slip badges, and keeps every status readable from its icon and text. The animation never plays for anyone whose device asks for reduced motion.

When something looks wrong

What you seeLikely causeFix
The landing page, no chartTask is emptyAdd a field to Task
Rows, but no barsStart and End are emptyAdd Start and End as Date columns
Bars back in 1970Start or End is a number (Sum or Count)Change the column to Date; use Earliest and Latest
No connector linesPredecessors without Task ID, or IDs that don't match exactlyAdd Task ID; check the IDs and separators
A task shows done at 1%A 0–100 Progress column with a 1 in itUse a 0–1 column
Progress is far too lowSum over several rows went above 1Use Average or Maximum
One task on two rowsA Columns or category field differs between its rowsMove that field to Tooltips
A column in Columns doesn't showThe task list is too narrow for itWiden Task list > Width
Some tasks have no Float in the tooltipA dependency cycle, or the task has no datesFind the loop in Predecessors
The critical path ignores Critical withinCritical flag is boundRemove it to use the computed path